Gurugram
08042756762
LIGHTNING PROTECTION SYSTEM (LPS) GOVERNMENT / PSU NIT – TECHNICAL SPECIFICATION GENERAL NOTE
The Lightning Protection System (LPS) shall be executed by a specialised and experienced agency.
The complete system design, drawings, calculations and technical details shall be submitted to the Consultant / Client for approval prior to execution.

The proposed LPS shall be properly interconnected with the existing Lightning Protection System available at site.
The quantities indicated are tentative and are provided for tender purpose only. Any additional items/components required for proper functioning and completeness of the LPS shall be deemed to be included in the contractor’s scope at no extra cost, and the system shall be complete in all respects.

SCOPE OF WORK

Supply, Installation, Testing and Commissioning (SITC) of Conventional Type Lightning Protection System as per IEC 62305, latest National Building Code (NBC) of India and applicable standards.

The scope shall include all accessories, fasteners, clamps, screws, bolts, nuts, supports, testing, documentation and all items necessary to make the system fully functional and complete in all respects.

All components shall conform to IEC 62561, EN, VDE and other applicable international standards.

TECHNICAL SPECIFICATION
1. Air Termination Conductor

SITC of 8 mm diameter solid Aluminium Conductor for horizontal air termination on terrace/roof.

Tested as per IEC 62561-2.

Testing shall be conducted in Government-approved / accredited third-party laboratory.

The conductor shall meet the requirements of IS / IEC 62305.

2. Terrace Conductor Holder (Flat Roof)

Terrace holder made of frost-resistant concrete.

Minimum weight: 1 kg per holder.

Installation spacing: 1 meter c/c.

Suitable for flat roof applications.

3. Universal Clamp

Universal clamp made of stainless steel.

Tested as per applicable standards.

Suitable for cross connections, T-connections and interconnections.

4. Expansion Piece

Expansion piece to be provided at every 20 meters.

Made of aluminium conductor.

Tested as per applicable standards.

Rated for 100 kA lightning current.

5. Parallel Connector

Parallel connector made of stainless steel.

Tested as per applicable standards.

Used for interlinking expansion piece and 8 mm aluminium conductor.

6. Parapet Conductor Holder

Supply of roof conductor holder for parapet walls:

Polyamide conductor holder

With M8 female thread / 7 mm diameter

M8 screw for fixing the conductor holder

Weather and temperature resistant from –35°C to +90°C

Installation spacing: 1 meter

Tested as per IEC 62561

Suitable for:

Round conductors Rd 8–10 to Rd 16

Flat conductors FL30

Including 2 Nos. M8 × 20 mm hexagonal bolts, high-grade stainless steel

TEMPORARY POWER & LIGHTING (LUMP SUM)

Lump sum charges for distribution, installation, operation and maintenance of temporary power supply and lighting for all agencies at site, including:

Tube lights / flood lights

Industrial sockets with MCB

Plug tops

ELCB and all required safety devices

The system shall ensure safe, continuous and uninterrupted power supply throughout the project duration.

The scope includes:

All floors

Shafts

Project office

Storage areas

Plug points and light fittings

The contractor shall also provide continuous maintenance of the temporary power distribution system for the entire duration of the project.

DRAWINGS & APPROVALS

Preparation of detailed shop drawings

Submission and revision until approval from Consultant / Client

Approval of drawings and works from Electrical Inspector

Obtaining charging permissions from CEIG / concerned authorities

MS TRENCH / SHAFT COVERS

SITC of MS covers for electrical trenches / shafts, fabricated from:

6 mm thick MS chequered plates

With suitable MS angle stiffeners

Proper lifting arrangement as per approved drawings

Painting system:

Primer coat

Red oxide coat

Two coats of finishing paint (approved colour)

SYSTEM STUDIES (THIRD-PARTY)

Arranging system studies for the complete electrical distribution system (Full SLD) through a competent third-party agency, including submission of reports in approved formats.

Credentials of testing agency to be submitted and approved by Consultant
(Efficienergy Consulting or equivalent approved agency).

Studies to include:

Arc-Flash Study

Load Flow Study

Short Circuit Study

Relay Coordination Study

Relay coordination and calibration shall be carried out as per approved PDC report.

FIRE SEALANT WORKS
A. Fire Sealant for Walls

Supply and installation of expanding firestop foam

Minimum 2 hours fire rating

Tested as per FM Approval Class No. 4990

Applicable for horizontal and vertical openings in floors/walls

Installation by trained applicators

Inclusive of packing materials

Aesthetic, water-tight finish

Wall thickness: 200 mm

Quantity based on actual gap size

B. Fire Sealant for Shafts

Supply and installation of Fire Barrier Mortar CP 636

Minimum 2 hours fire rating

Tested as per FM Approval Class No. 4990

For service shafts through fire-rated floors and walls

Minimum thickness: 70 mm

Product shall bear UL & FM approval marking

Inclusive of all materials and application

Aesthetic, water-tight finish

Quantity based on actual gaps

Dec 18th, 2025 4:34 PM

Keywords