Gurugram
08042756762
+919990645119

LIGHTNING PROTECTION SYSTEM (LPS) GOVERNMENT / PSU NIT – TECHNICAL SPECIFICATION GENERAL NOTE

The Lightning Protection System (LPS) shall be executed by a specialised and experienced agency. The complete system design, drawings, calculations and technical details shall be submitted to the Consultant / Client for approval prior to execution. The proposed LPS shall be properly interconnected with the existing Lightning Protection System available at site. The quantities indicated are tentative and are provided for tender purpose only. Any additional items/components required for proper functioning and completeness of the LPS shall be deemed to be included in the contractor’s scope at no extra cost, and the system shall be complete in all respects. SCOPE OF WORK Supply, Installation, Testing and Commissioning (SITC) of Conventional Type Lightning Protection System as per IEC 62305, latest National Building Code (NBC) of India and applicable standards. The scope shall include all accessories, fasteners, clamps, screws, bolts, nuts, supports, testing, documentation and all items necessary to make the system fully functional and complete in all respects. All components shall conform to IEC 62561, EN, VDE and other applicable international standards. TECHNICAL SPECIFICATION 1. Air Termination Conductor SITC of 8 mm diameter solid Aluminium Conductor for horizontal air termination on terrace/roof. Tested as per IEC 62561-2. Testing shall be conducted in Government-approved / accredited third-party laboratory. The conductor shall meet the requirements of IS / IEC 62305. 2. Terrace Conductor Holder (Flat Roof) Terrace holder made of frost-resistant concrete. Minimum weight: 1 kg per holder. Installation spacing: 1 meter c/c. Suitable for flat roof applications. 3. Universal Clamp Universal clamp made of stainless steel. Tested as per applicable standards. Suitable for cross connections, T-connections and interconnections. 4. Expansion Piece Expansion piece to be provided at every 20 meters. Made of aluminium conductor. Tested as per applicable standards. Rated for 100 kA lightning current. 5. Parallel Connector Parallel connector made of stainless steel. Tested as per applicable standards. Used for interlinking expansion piece and 8 mm aluminium conductor. 6. Parapet Conductor Holder Supply of roof conductor holder for parapet walls: Polyamide conductor holder With M8 female thread / 7 mm diameter M8 screw for fixing the conductor holder Weather and temperature resistant from –35°C to +90°C Installation spacing: 1 meter Tested as per IEC 62561 Suitable for: Round conductors Rd 8–10 to Rd 16 Flat conductors FL30 Including 2 Nos. M8 × 20 mm hexagonal bolts, high-grade stainless steel TEMPORARY POWER & LIGHTING (LUMP SUM) Lump sum charges for distribution, installation, operation and maintenance of temporary power supply and lighting for all agencies at site, including: Tube lights / flood lights Industrial sockets with MCB Plug tops ELCB and all required safety devices The system shall ensure safe, continuous and uninterrupted power supply throughout the project duration. The scope includes: All floors Shafts Project office Storage areas Plug points and light fittings The contractor shall also provide continuous maintenance of the temporary power distribution system for the entire duration of the project. DRAWINGS & APPROVALS Preparation of detailed shop drawings Submission and revision until approval from Consultant / Client Approval of drawings and works from Electrical Inspector Obtaining charging permissions from CEIG / concerned authorities MS TRENCH / SHAFT COVERS SITC of MS covers for electrical trenches / shafts, fabricated from: 6 mm thick MS chequered plates With suitable MS angle stiffeners Proper lifting arrangement as per approved drawings Painting system: Primer coat Red oxide coat Two coats of finishing paint (approved colour) SYSTEM STUDIES (THIRD-PARTY) Arranging system studies for the complete electrical distribution system (Full SLD) through a competent third-party agency, including submission of reports in approved formats. Credentials of testing agency to be submitted and approved by Consultant (Efficienergy Consulting or equivalent approved agency). Studies to include: Arc-Flash Study Load Flow Study Short Circuit Study Relay Coordination Study Relay coordination and calibration shall be carried out as per approved PDC report. FIRE SEALANT WORKS A. Fire Sealant for Walls Supply and installation of expanding firestop foam Minimum 2 hours fire rating Tested as per FM Approval Class No. 4990 Applicable for horizontal and vertical openings in floors/walls Installation by trained applicators Inclusive of packing materials Aesthetic, water-tight finish Wall thickness: 200 mm Quantity based on actual gap size B. Fire Sealant for Shafts Supply and installation of Fire Barrier Mortar CP 636 Minimum 2 hours fire rating Tested as per FM Approval Class No. 4990 For service shafts through fire-rated floors and walls Minimum thickness: 70 mm Product shall bear UL & FM approval marking Inclusive of all materials and application Aesthetic, water-tight finish Quantity based on actual gaps
 2025-12-18T11:04:53

Keywords